Construction Continues on South Greeley Lot

CHAPPAQUA, N.Y. -- The South Greeley Parking Lot Project proceeded another step Monday as construction crews installed the drainage system. A large crane was parked in the South Greeley lot to lift the storm drains into place in the front of parking lot. In the rear, the lighting median has been installed.

Construction on the parking lot is expected to continue throughout August. The South Greeley Parking Lot Project is expected to be completed by Labor Day.

The parking lot remains partially open to traffic, with about eight parking spots available to New Castle shoppers and visitors.

 